Wind turbine base production line expansion project change EIA enterprise publicity

2019-12-21


Name and summary of 1. construction project
Project Name: Wind turbine base production line reconstruction and expansion project
Construction unit: Xiangtan Yongda Machinery Manufacturing Co., Ltd.
Project location: 1# plant is located at No.1 Fulin Road, Xiangtan Jingkai District, and 2# plant is located at No.1 Dazhong East Road, Xiangtan Jingkai District;
Overview of project construction: the contents to be changed this time: 2 spray booths will be reduced in the coating line of 2# plant area, and the environmental protection treatment facilities will remain unchanged; The new coating line in the 1# plant area includes 2 spray booths, 1 water washing room, 1 polishing room and 1 drying room, and at the same time, new supporting waste gas and wastewater treatment devices will be built. This change only involves the adjustment of production equipment, and the total production content and scale remain unchanged.
Environmental impact and measures: the environmental protection settings of 2# plant area have not changed; The adjustment contents of 1# plant area are as follows: 1. Waste water: the cleaning waste water from the cleaning room is recycled for cleaning after being treated by the "air flotation filtration" process. 2, waste gas: mainly paint grinding dust, coating organic waste gas VOCs and hot stove gas waste gas. Dust is discharged from a 15m high exhaust cylinder after being treated by supporting dust removal facilities. Paint organic waste gas is collected by a fan, purified by "filter cotton UV photolysis activated carbon" and discharged through a 15m high exhaust cylinder. 3, solid waste: mainly for the coating line raw and auxiliary materials packaging and other general industrial solid waste; paint surface grinding dust collection, paint residue, waste paint bucket and waste filter material and other hazardous waste. Except for the containers that can be recycled by the manufacturer, the rest of the hazardous waste shall be handled by qualified units. 4. Noise: noise of main water pumps, fans and other equipment. After the existing wall sound insulation, and take measures such as shock absorption, noise reduction, can effectively reduce the impact of its noise on the surrounding environment.
The project has an impact on the environment during the construction and operation process, and the company will conduct treatment according to the environmental protection standards allowed by the state and local governments to ensure that the pollutants are discharged up to the standard.
II. Working procedures and main contents of environmental impact assessment
The working procedure of environmental impact assessment is roughly divided into three stages: the first stage is the preparation stage, collecting relevant documents, conducting preliminary field investigation, and preparing the environmental impact assessment work plan; the second stage is the formal work stage, further engineering analysis and environmental status investigation, and environmental impact analysis and evaluation; the third stage is the report preparation stage, the main work is to summarize and analyze various data and data obtained from the second stage of work, give conclusions, and complete the preparation of the environmental impact report.
Main work content: According to the environmental impact assessment method, the evaluation work is carried out in accordance with the guidelines, and the evaluation focuses on engineering analysis, atmospheric environmental impact assessment, and economic and technical demonstration of pollution prevention and control measures.
Main matters 3. soliciting public opinions
The full version of the Environmental Impact Change Report of the Wind Turbine Generator Seat Production Line Reconstruction and Expansion Project can be downloaded here. The purpose of public participation is to collect the views, requirements and wishes of the public on the project construction within the scope of influence of the project. If the public has any objection to the working procedures and contents of the project or EIA work, please contact the project unit or EIA unit within 10 working days.
Main ways of 4. public input
The public can contact the project construction unit or EIA unit by telephone, fax, letter, etc.
Name and contact information of construction unit of 5. project
Construction unit: Xiangtan Yongda Machinery Manufacturing Co., Ltd.
Address: No.1 Fulin Road, Jingkai District, Xiangtan
Contact: Liu Xiong
Contact number: 13973278979
6. name and contact information of the environmental impact assessment agency undertaking the assessment work
Evaluation Unit: Hunan State Grid Environmental Science Research Institute Co., Ltd.
Address: Paper Research Institute, Yuetang District, Xiangtan City
Contact: Zhang Langwei
Tel: 0731-55881598